← Back to projects

Rapid Manufacturing Solution · Design, Machining & Assembly

Polyurethane Mold Extension System

A two-week production solution that allowed manufacturing to meet an urgent new dimensional specification while the permanent mold remained in development.

OrganizationGlobe Composite Solutions
DateSpring 2026
RoleEnd-to-End Project Owner
Core SkillsSolidWorks · Machining · Assembly
Polyurethane Mold Extension System
2 weeksConcept to production
2.5 in.Additional required length
$40K/dayApproximate delay exposure

The Urgency

Production could not wait.

Updated specifications required parts 2.5 inches longer than the existing molds could produce. The permanent dual-cavity mold would take months to fabricate, while every delayed production day represented approximately $40,000 in lost revenue.

Design Strategy

Make the temporary solution easier to operate.

After reverse engineering an existing extension concept, I designed a new bottom-mounted system. Because the extensions stayed on the mold base, operators did not need to remove them during every demolding cycle.

Manufacturing Workaround

Eliminating a four-week coating delay.

The required non-stick coating had a four-week lead time. I reused coated aluminum from discontinued tooling and added Teflon tape where needed, allowing the extensions to enter service immediately.

To make the reused aluminum fit the available CNC machines, I purchased an aluminum-cutting circular saw and cut the raw plates by hand before completing the precision machining operations.

Execution

Complete ownership from stock to production.

I designed every component in SolidWorks, sourced materials, hardware, O-rings, and tooling, purchased a metal-cutting circular saw, processed the aluminum stock, machined every component in-house, and personally assembled the completed system.

The finished extensions enabled production to begin manufacturing parts that met the new specification while the permanent mold continued through development.

My Contributions

What I owned and delivered.

  • Reverse engineered the existing concept and redesigned it as a bottom-mounted extension system
  • Avoided the coating delay by reusing coated aluminum and developing a practical release-surface workaround
  • Hand-cut the aluminum stock, machined the components, and assembled the complete system
  • Delivered the project from concept to production in two weeks while protecting an estimated $40,000 per day
Next project Polyurethane Test Molds